What Probability Impact (L/M/H) Mitigation
Elewijt Center is not available (e.g. burns down) <1% H Cancellation policy
Not all payments have been received in time 99% M Agile Systems provides financial buffer
Webserver crash 5% M Monitor wiki (by more than one person)
Participants arrive late for the OpeningSession 99% H Start OpeningSession not too early (e.g. at 10:00am)
Participant gets (physically) hurt during conference 1% M Insurance, Elewijt has medication available. Do they have a first-aid person?
Too little registrations or none at all (<20) 10% H Minimum number of participants = 20; Cancellation policy --> correct nr of participants and hotel rooms : 1 week before conference date
Too many registrations (>40) 10% L Close registration; accept people on first-come first-served basis
PayPal? problems 5% L People pay later -> have some financial buffer
In case of severe problems; in case of problems, ask people to pay by bank transfer
Too many payments through PayPal? (=delay in receiving money) 50% M Financial buffer
Unpaid registrations 50% L Require payment in advance + financial buffer
More participants than will fit in the Elewijt hotel rooms 10-20% M Hunt and select 3 alternative hotels, possibly through Elewijt
Traffic problems (eg train or plane strikes) --> a lot of participants simply can't get there 20% M Start the (official) OpeningSession later; let the participants that are present self-organise; do an OpeningSession each morning
A princess is scheduled to arrive at the conference centre 50% (it happened at one of the xp days) M possible change of rooms, time needed to re-negotiate with elewijt